Unpriced bill of quantities
A bill of quantities (BoQ) is an important document prepared by a quantity surveyor (or cost consultant) which itemises the type, form and amount of material that will be required on a project, including quantities of labour and other items. Quantities may be measured in number, length, area, volume, weight or time and are known as ‘measured quantities’.
A BoQ may be priced, in that prices are given by suppliers for each item. The sort of considerations that might be considered when pricing work include current costs of materials, machinery hire and transport, wages, overhead expenses associated with administration and so on.
In contrast, an ‘unpriced bill’ is a BoQ that is essentially a template: it breaks down the work required on a project into exact tasks but has no measured quantity (or price) by each task. The information is arranged into a form that is suitable for direct pricing by a supplier, describing the individual items to be priced and the numbers, amounts or quantities of each required for the project.
It is up to the company tendering for the project to insert against each task what it will charge the client to complete that task. This priced bill of quantities constitutes the tenderer's offer. It is the unpriced bill of quantities, but with the tenderer’s rates, costs and totals added.
The preparation, by the client’s consultants, of an unpriced bill of quantities means all tendering contractors will be pricing the same quantities (rather than taking-off quantities from the drawings and specifications themselves), and so provides a fair and accurate system for tendering. It also makes it possible to compare both the overall price and individual items directly with other tenderers’ offers, allowing a detailed assessment of which aspects of a tender may offer good or poor value. This information can assist with tender negotiations.
[edit] Related articles on Designing Buildings Wiki
- Approximate bill of quantities.
- Approximate quantities.
- Bill of quantities.
- Bill of quantities breakdown structures.
- Bill of quantities software.
- Common Arrangement of Work Sections (CAWS).
- Common mistakes in bill of quantities.
- Comparison of SMM7 with NRM2.
- Elemental bill of quantities.
- Firm bill of quantities.
- How to take off construction works.
- Measurement.
- New Rules of Measurement.
- NRM1.
- NRM2.
- NRM3.
- Standard Method of Measurement (SMM7).
- Taking off.
- Tender documentation.
- Tender pricing document.
- Uniclass.
- Working up construction works.
- Work package bill of quantities.
- Work section bill of quantities.
Featured articles and news
Editor's broadbrush view on forms of electrical heating in context.
The pace of heating change; BSRIA market intelligence
Electric Dreams, Boiler Realities.
New President of ECA announced
Ruth Devine MBE becomes the 112th President of the Electrical Contractors Association.
New CIAT Professional Standards Competency Framework
Supercedes the 2019 Professional Standards Framework from 1 May 2025.
Difficult Sites: Architecture Against the Odds
Free exhibition at the RIBA Architecture Gallery until 31 May.
PPN 021: Payment Spot Checks in Public Sub-Contracts
Published following consultation and influence from ECA.
Designing Buildings reaches 20,000 articles
We take a look back at some of the stranger contributions.
Lessons learned from other industries.
The Buildings of the Malting Industry. Book review.
Conserving places with climate resilience in mind.
Combating burnout.
The 5 elements of seiri, seiton, seiso, seiketsu and shitsuke.
Shading for housing, a design guide
A look back at embedding a new culture of shading.
The Architectural Technology Awards
The AT Awards 2025 are open for entries!
ECA Blueprint for Electrification
The 'mosaic of interconnected challenges' and how to deliver the UK’s Transition to Clean Power.
Grenfell Tower Principal Contractor Award notice
Tower repair and maintenance contractor announced as demolition contractor.